Victorian Public Holidays and Your P6 Schedule: What Most Planners Get Wrong

Victoria observes the standard national public holidays plus three of its own: Labour Day, the Friday before the AFL Grand Final, and Melbourne Cup Day (metro Melbourne only). Victoria also treats Easter Saturday as a public holiday, which most other states don't. Get any of these wrong in a P6 calendar and every downstream date — early finish, late finish, float — is quietly wrong too.

2026

HolidayDateNote
New Year's DayThu 1 Jan 2026 
Australia DayMon 26 Jan 2026 
Labour DayMon 9 Mar 2026VIC only
Good FridayFri 3 Apr 2026 
Easter SaturdaySat 4 Apr 2026VIC only, not national
Easter SundaySun 5 Apr 2026 
Easter MondayMon 6 Apr 2026 
ANZAC DaySat 25 Apr 2026No substitute day for weekend
King's BirthdayMon 8 Jun 2026 
AFL Grand Final FridayFri 25 Sep 2026VIC only, date moves yearly
Melbourne Cup DayTue 3 Nov 2026Metro Melbourne only
Christmas DayFri 25 Dec 2026 
Boxing DaySat 26 Dec 2026Substitute Mon 28 Dec 2026

2027

HolidayDateNote
New Year's DayFri 1 Jan 2027 
Australia DayTue 26 Jan 2027 
Labour DayMon 8 Mar 2027VIC only
Good FridayFri 26 Mar 2027 
Easter SaturdaySat 27 Mar 2027VIC only, not national
Easter SundaySun 28 Mar 2027 
Easter MondayMon 29 Mar 2027 
ANZAC DaySun 25 Apr 2027No substitute day for weekend
King's BirthdayMon 14 Jun 2027 
AFL Grand Final FridayFri 24 Sep 2027VIC only, date moves yearly
Melbourne Cup DayTue 2 Nov 2027Metro Melbourne only
Christmas DaySat 25 Dec 2027Substitute Mon 27 Dec 2027
Boxing DaySun 26 Dec 2027Substitute Tue 28 Dec 2027
Working Days Calculator — Victoria

Why this trips planners up

Two things go wrong most often. First, planners import a generic "Australia" calendar into P6 that only carries national holidays — missing Labour Day, Easter Saturday, AFL Grand Final Friday and Melbourne Cup Day entirely. Second, the AFL Grand Final Friday date isn't fixed years in advance the way Christmas is — it depends on the AFL's finals fixture for that season, so a calendar built in one year for a schedule running two or three years out needs updating once the date is confirmed, not left on last year's date.

What this means for planners

Why AFL Grand Final Friday catches people out every year

Unlike every other date on the Victorian calendar, Grand Final Friday isn't known with certainty until the AFL publishes its finals series draw, typically only a few months before the day itself. A P6 calendar built well in advance of a project's actual delivery window can easily be scheduled with last year's date, or with no allowance for the holiday at all if it was built before the date was public.

How to model it in P6 as a calendar exception

Treat it the same way as any other single-day exception: add it as a non-working day to every calendar that governs site or delivery activities, and flag it in your document control process as a date to revisit and reconfirm each year once the AFL fixture is released — not a one-time calendar setup you can forget about.